High Meadows
HIGH MEADOWS PROJECT UPDATE
- Town Received 3 applications for qualified firms:
The Community Builders and Habitat for Humanity
The Carabetta Companies
Dakota Partners
- Proposal Links are below
- Recordings of each of the Developer Interviews with Advisory Members and Town Staff are available on the link below
- Each Developer committed to paying the $1.5M purchase price.
- All proposals met the minimum requirement that 20% of rental units had to be affordable for persons with incomes at or below 80% AMI. (Area Median Income)
- The Advisory Committee selected Dakota Partners Proposal, https://dakotapartners.net/, to create 202 units in combination of rental and for-sale duplex units. Based on this recommendation, a Conditional Award has been made to the developer. The Hamden Legislative Council is responsible for making the final determination.
- Colliers Advisory Service completed an analysis of the proposals received. The Dakota proposal received the highest ranking. Colliers Analysis is available on the link below
- For sale units are not included in affordability requirements. Projected sales prices are based on current costs and market conditions.
- Town will provide assumptions on impacts to schools and other public service costs.
- Any potential traffic impacts will be considered by the Hamden Planning and Zoning Commission. The Developers were not required to provide a traffic studies at this stage in the process.
- Dakota Partners’ proposal prioritizes the preservation of open space. Proposal contemplates that a portion of the property will be transferred to the Hamden Land Conversation Trust.
- The Town has not committed to providing any direct subsidies for this project.
HIGH MEADOWS ESTIMATED PROJECT SCHEDULE
Developer Selection/Recommendation | March 2024 |
Town post Developer interviews Sessions, proposals and completed analysis on Economic Development Website (www.hamdenedc.com) | April 2024 (information will not be posted until Developer formally accepts Town conditional offer) |
Developer Presentation to Community on proposed Development | May 2024 (Date and location TBD) |
Presentation to Legislative Council for Approval | May 2024 Subject to Change |
Execution of Development Agreement between the Town and Selected Developer |
September 2024 |
Developer Submission to Planning and Zoning Commission for project approval | March 2025 |
Planning and Zoning Commission Approval of project | May 2025 |
Execution of Development Agreement between the Town of Hamden and the Developer Developer has agreed to the Towns purchase price of $1.5M |
June 2025 |
Closing on Land between Town of Hamden, State of CT and selected Developer | June 2025 |
Anticipated Construction Start | August 2025 |
Click link below to view RFP 24-01 Redevelopment Opportunity of the High Meadows Property
RFP 24-01 Redevelopment opportunity of the High Meadow property
Click links below to view RFP 24-01 Proposals received
The Carabetta Team Investors Network LLC Proposal to RFP 24-01
The Community Builders Proposal to RFP 24-01
Click links below to view Colliers Analysis of Proposals
The Community Builders Affordable Option
Click links below to view RFP 24-01 interviews
Carabetta Interview February 1, 2024 at 9:01 am
Passcode: *RV@nm6U
The Community Builders Interview February 1, 2024 at 10:02 am
Passcode: 1E*MqM9t
Dakota Partners Interview February 1, 2024 at 10:59 am
Passcode: 5zOF+f3!
Click link below to view Colliers International Market Study to RFP 24-01 Proposals
Colliers International Market Study